In this project, site selection, planning, designing and financing of port infrastructure was done
This is the methodology followed in order to select a suitable site for port infrastructure.
Commodity selection, traffic projection, layout design, financial feasibility of the port is conducted in detail.
This is the methodology followed in order to select a suitable site for port infrastructure.
Finally the site selected on basis of elimination method was Mocha.
Commodity selected are: Urea, Textiles, Auto ancillary parts and fisheries.
This slide shows, port wise Urea handling capacity for different years.
This slide shows the traffic projections of urea. By 2053 the projected demand is be 3.77MMT
This slide shows, urea handling capacity of the terminal for the 3 phases.
Break Water is planned and designed in order to shield the Port from harmful currents. Tetrapods have been used as armor layer of the Breakwater