Aayush Agrawal

5146

CONSTRUCTION TECHNOLOGY- 1

The project is a compilation of my work done, observations made on site and my understanding of the methods of construction used on site.The course gave me a basic knowledge and understanding of the work done on the construction site. I did a detailed study on the construction methods which included analyzing the labor cost, labor distribution, labor productivity, material usage, material wastage and material cost.I visited the site for a duration of 6-8 hrs , once or twice a week , over a period of almost 4 months.


Report Content

SITE INTRODUCTION

LINE OUT(ACTIVITY)

EXCAVATION(ACTIVITY)

MODEL MAKING(SECURITY ROOM)

REINFORCEMENT OF STAIRCASE

REINFORCEMENT OF STAIRCASE

REINFORCEMENT OF STAIRCASE

CALCULATION OF STEEL

JOB LAYOUT