construction technology II~ FORMWORK OF LIFT SHAFT  1. PROCEDURE AND LOADTRANSFERMECHNISM ~ ENOUGH OF MATERIAL AND LABOUR IS MADE AVALIABLE ON SITE MATERIAL SHOULD BE PROPERLY CHECKED BEFORE USE ONCE  ~ THESE PRE-REQUISITE ARE DONE THE BOTTOM MOST PART OF LIFT IS ERRECTED  ~ SO AS SO TO GIVE SUPPORT TO OTHER SIDES AS WELL AS TO MAKE IT MORE CONVINIENT TO WORK  ~ 0NCE BOTTOM FORMWORK IS DONE A GRID OF SIDE  ~ FORMWORK IS MADE AND THEN ERECTED VERTICALLY    ~ AFTER COMPLECTION OF REINFORCEMENT THE EXTERNAL SIDED ARE ERECTEDIN SIMILLAR FUNCTION . ~ THEN UPTO LOAD TRANSFER MECHANISM  


Report Content

INTRODUCTION

ON SITE PHOTOS

PROCEDURE

SEQUENCE

POSTER