As a part of studio, for BIM & Lean Implementation, one Pilot Project and one Live Project were studied. The studio project undertaken by the group is a Commercial Building spread over an area of 65000 sqm. It includes the construction of two towers (A and B) each of 13 floors with 3-Basements. The project's scope was 4th and 5th floor of Tower A. Model development of architectural, structural and MEPF models, Quantity Takeoff, Clash detection, 4D Simulation, Last Planner System were studied and carried out in detail and suitable proposals were also suggested as a part of the study. 


Report Content

Phase Planning for Pilot Project

4D Simulation using Navisworks

Site Layout Analysis for Live Project

Site Logistics Plan

Quantity Takeoff and Cost Estimation comparison of Manual v/s Revit

Application of Value Engineering

Functional and Time based analysis on application of Value Engineering

4D Simulation for Live Project

4D Simulation

4D Simulation on the basis of LPS