For a richer surfing experience on our website, please update your browser. Update my browser now!
The project training was done at Elevated Metro project Ahmedabad Metro Reach-2 (Thaltej to west Ramp) under the guidance of contractor Tata Projects Limited(CCECC TPL JV). The project training encompassed the study of construction Methodology, Cost Analysis, Time Cycle Analysis, Technology adopted, etc. At the end of the semester, a concise project report was prepared for station elements namely Pile, pile Cap, Pier, Pier Arm, and I-girder. This portfolio comprises the details related to overall Project, Cost Breakdown, Pier and I-Girder casting and Erection, etc.