• Prepare the General arrangement of bridge as per industrial requirement.• Apply the criteria for the suitability/feasibility of the various types of the superstructure.• Analysis, design and detail the superstructure, sub structure and foundation.• Apply the codal regulations for bridge loadings as per IRC-06 and design methodology as per IRC 112 and IRC 78.


Report Content

Project Details

Parametric Approach, Initial Exercise

General Arrangement

Grillage Analysis

Loading and Stability

Bending Moment and Preliminary Prestress Design

Cable Profile and Prestressing Details

Actual Loss and Stress Summary

Pier Forces and Design

Pier Detail and Foundation Design