The semester included the study of the Ahmedabad metro project from conceiving stage to commissioning stage of the project across the project life cycle. The main emphasis was laid upon the planning aspects across every project stage. A live example of the case study was taken in conjunction with prevailing construction practices including ethos and ethics of engineers.


Report Content

Casting yard locations and distances

casting yard scope of work for reach-2

Casting yard initial space planning

casting yard space utilisation

Number of bed and stacking capacity calculation

Number of bed and stacking capacity calculation

services details

facility details

office details

site logistics and optimisation