Shah Siddharth Rajivkumar

CM4001-2

The Iconic Curve

We analysed and implemented Integrated Construction Practices for Iconic Curve, a G+31 twisted commercial tower in GIFT City. We began by understanding project details, stakeholder roles, and challenges, then prepared the EIR and BEP to standardize BIM processes. By aligning LOD with LOS, we developed coordinated discipline models and applied the Last Planner System to improve planning reliability. Through clash detection, we resolved inter-disciplinary conflicts, while BIM-based quantity take-off improved accuracy over manual methods. We optimized the site layout and path of travel, and used 4D–5D simulations for sequencing and cost control. Overall, we achieved better coordination, reduced rework, and stronger project governance.