Hruthick Ajay S G

CT2036

The Kutch Gateway

This project showcases the 1st segment of the design and engineering of a new high-speed corridor connecting Rapar to Dholavira, executed with a focus on achieving a cost-effective, safe, and sustainable infrastructure solution.


Report Content

The project is situated in the Plain Terrain and Arid to semi-arid climate of Rapar in eastern Kachchh, where the need for a faster route is essential to distribute increasing traffic.

The alignment planning evolved from an Initial Iteration with high costs and social impact to a Final Iteration that is the shortest and fastest route, avoiding obstacles like dense farmland and wetlands.

The Horizontal Alignment is designed for a Ruling Design Speed of 80 Kmph and incorporates a minimum radius of approximately 164m and a maximum super-elevation of 7% for safety and centrifugal force counteraction.

GIS Analysis guided the route selection to utilize the large 66.9%, Agriculture area and showed no streams above Strahler Order 4 were detected, significantly reducing the need for expensive bridges.

The Alignment of Road features a near-perfect Cut 75,209.51 cubic meters to Fill 65,793.34 cubic meters balance, minimizing the need for external material handling, while Soil Testing ensures the ground's suitability for road construction.

The Pavement Design consists of four layers—Wearing Course (BC), Binder Course (DBM), Base Course (WMM), and Sub-base (GSB)—and the typical Cut and Fill Cross Sections show the total roadway width of 7m carriageway plus shoulders and drains.

The detailed Drainage plan utilizes a chainage table and catchment maps to precisely locate side drains with a Typical Side Drain Earthen Cross Section of 0.734m top width and 0.6m depth for efficient runoff management.

The plan incorporates various Road Safety measures, including Warning and Informational Signs, and details the design of the 3-way and 4-way intersections to manage traffic flow and enhance safety.

The Cost Analysis provides a detailed layer-wise cost breakdown for the pavement structure (GSB, WMM, DBM, BC), accounting for material, transport, machinery, and labor costs to ensure the design is financially feasible.

The Vertical Alignment profile and accompanying table confirm that the Adopted Curve Length (L) consistently meets or exceeds the calculated requirement, ensuring superior sight distance and ride quality.