Savaliya Darshil Pravinbhai

UM4006

VIRASAT DEVELOPMENTS LLP - ARAVANTA CREST

This portfolio traces a mixed-use project in Shilaj, Ahmedabad, from forming the developer firm to presenting a funding proposal to an Investment Committee. The land was secured through a joint development agreement, with homes and retail planned together on one site. The work studies the local market, explains the choice of an LLP, and sets out how the built area was shared with the landowner. It then builds the cost and cash-flow model, the funding plan, and tests the returns.


Report Content

The firm and the site. Virasat Developments LLP was formed by five equal partners with Rs. 25 Cr of equity, and the LLP structure was chosen on six weighted criteria, with capital access weighted highest at 25%. The 6,329.11 sq m plot in Shilaj lies 400 m from SP Ring Road and fronts a 36 m road. My role covered land selection, the mixed-use proposal, the unit mix and area split, the viability numbers and the Rs. 30 Cr pitch to the Investment Committee.

Product, JDA and pricing. Under the joint development agreement, the landowner receives 65 finished units (21.8% of the built area), and the developer keeps 232 units (78.2%). The project has 297 units: 265 homes and 32 shops. Sales start at Rs. 4,700 per sq ft with a 7% annual escalation, which adds Rs. 25.69 Cr and brings developer revenue to Rs. 225.98 Cr.

Cost, funding and returns. The total project cost is Rs. 167.80 Cr, of which construction makes up 68.2%. Customer advances fund 67.2% of the cost, with the balance coming from Rs. 25 Cr of promoter equity and Rs. 30 Cr of Committee equity at 20%. Construction spend peaks at Rs. 17.17 Cr per quarter. The project gives a 33.4% IRR against a 19.10% hurdle rate, an NPV of Rs. 17.59 Cr and a profit of Rs. 58.18 Cr.

Cash flow, exit and risk. Cumulative cash reaches its lowest point of minus Rs. 54.36 Cr in Year 1, which Rs. 55 Cr of equity covers without bank debt. The cash position turns positive in Year 3, when the Committee's capital and preferred return are repaid first. A combined 10% price fall and 10% cost rise reduces profit by 57.4% to Rs. 24.81 Cr, but the project stays profitable.