In-Situ Slum Rehabilitation through a Public–Private Partnership (PPP) Vasant Kuva Na Chhapara, Ambawadi–Paldi, Ahmedabad.  The project proposes to rehabilitate 384 households on a 7,122 sq. m AMC site. By rebuilding on the existing site, residents can remain close to jobs, public transport and neighborhood services. Under the PPP model, the public authority facilitates approvals and infrastructure, while the private developer finances, designs and constructs the project. - Rehabilitation proposal . Three G+7 residential buildings with ground-floor parking, an Anganwadi, a health facility and restoration of the existing temple. Site constraints, The site falls within a Transit-Oriented Zone with a permissible FSI of 4.0. The study identifies a 24 m height limit linked to the 12 m approach road and a 30 m railway setback. Rehabilitation requires over half the site, leaving limited land for free-sale development.  Financial feasibility-the study compares selling the remaining land with two options for constructing market-rate housing and retail. It recommends selling the free-sale parcel and monetizing eligible Transferable Development Rights (TDR) to fund rehabilitation with lower upfront investment.  Projected outcome - At an assumed land sale price of ?1.5 lakh per sq. yd, the preferred option projects ?9.9 crore net profit, 25.36% IRR, and break-even in Quarter 8.


Report Content

Policy Framework and Site Selection- The study applies Gujarat’s 2013 Slum Rehabilitation Policy to Vasant Kuva Na Chhapara, a site on Ahmedabad Municipal Corporation land at the Ambawadi–Paldi interface.

Site Details and Immediate Context - The 7,122 sq. m site contains 384 existing dwellings. The site analysis maps road access, railway and metro setbacks, surrounding land uses, and gently undulating terrain.

Site Observations, SWOT and Micromarket Site photographs document the settlement and its edges. The SWOT analysis highlights strong transit connectivity alongside railway-related constraints, while the market survey finds that residential projects account for 83% of nearby developments.

Product Mix and Market Absorption Across the areas studied within 1.5 km, 3 BHK homes dominate the residential mix and show the most consistent absorption among the projects reviewed. These findings inform a mixed-use option with predominantly 3 BHK homes and ground-floor retail.

Slum Redevelopment Case Studies Kailashnagar, Dharavi and Shaktinagar illustrate different redevelopment challenges, from securing resident consent and protecting livelihoods to funding long-term building maintenance.

Preliminary Development Analysis The preliminary assessment tests how 384 rehabilitation homes and a potential free-sale component can fit on the site. It also sets out built-up area, construction cost and pricing assumptions, with a 15.88% discount rate for the financial appraisal.

Comparative Financial Analysis Of the three options assessed, the land-sale model has the lowest cash outflow and the highest projected IRR at approximately 25%. All three options provide 384 rehabilitation homes.

Land-Sale Model and Cash Flow The model projects ?66.66 crore in revenue from land and transferable development rights (TDR) sales, yielding a net profit of ?9.9 crore and an IRR of 25.36%. Most proceeds are expected in the final quarter.

Construction Timeline and Break-Even The two-year schedule places approvals in Q1, phases rehabilitation construction and TDR sales, and schedules the land sale in Q8, when cumulative revenue is projected to exceed project costs.

Sensitivity Analysis and Conclusion The sensitivity analysis estimates a break-even land sale price of approximately ?1.25 lakh per sq. yd. Given the 24 m height limit, 30 m railway setback and rehabilitation land requirement, the study favours selling the free-sale parcel and utilising eligible TDR.