A workshop covering design of a concentric RCC ring silo (21 m and 15 m diameter) for cement and pulverized lime, covering wall pressures as per IS 4995, bin walls, hopper, ring beams, temperature effects and crack width. The studio project, Transfer Tower TT3, is a 72 m, 12-floor steel staging structure serving a coal handling plant in Bihar. Work flows from flooring iterations and raised, hanging platforms to a 3D model analyzed for wind and seismic loads, then design of built-up columns and beams, bracing, purlins, monorails, connections and base plates as per IS 800, IS 875 and IS 1893.