MAHATMA GANDHI (OLD) BRIDGE

Mahatma Gandhi (Old) Bridge, a 427 m, 18-pier RCC T-beam bridge constructed in 1942 over the Sabarmati River in Ahmedabad, was assessed for structural adequacy and rehabilitation after 83 years of service. Materials were confirmed as M20 concrete and Fe240 steel through NDT and core testing. Visual inspection identified 11 distress types including honeycombing, exposed reinforcement, and biological growth. Structural analysis under IRC 112:2020 revealed moment and shear deficits in the T-beam girders, necessitating superstructure strengthening. Steel plate bonding and FRP wrapping were recommended as the most practical interventions, while the pier and pier cap substructure were found adequate with no strengthening required.

View Additional Work

Report Content

INTRODUCTION

GENERAL ARRANGEMENT DRAWING

DAMAGE MAPPING

PHOTOGRAMMETRY

STUDY & DESIGN OF DECK SLAB & GIRDER

T-BEAM DIANA MODELLING

DESIGN OF PIER & PIER CAP

GENERAL REPAIR METHODS

STRENGTHENING METHODS FOR DECK SLAB & GIRDER

CONCLUSION