Mass concreting operations in Indian high-rise construction involve continuous pours of 5,000-12,000 m³, demanding precise logistics, thermal control, and risk management. This research develops a validated planning framework comprising a 51-risk register across five categories, three planning models (Cost Fixed, Time Fixed, Balanced Optimum), and a decision-support dashboard. Model 3 is the Balanced Optimum using 8 RMC plants at ?6.12 Crore emerged as the recommended configuration, confirmed by all three expert validators. A key finding: the time-cost relationship is non-linear, and logistics, not mix design, is the critical controlling factor.