Jeffy Thomas George

CM4050

PCM24150

This Directed Research Project addresses persistent delays and rework during the Design Development phase of healthcare construction in India, where BIM adoption remains tool-centric rather than process-centric. Using a System Dynamics methodology, twenty-one DD-stage challenges are identified through literature and expert interviews, prioritised via a statistically validated RII survey of 24 industry respondents, and modelled in Vensim across five governance scenarios over a 50-month horizon. The simulation confirms that only Integrated BIM Coordination approaches delay stabilisation. Findings are operationalised through a working prototype integrating Autodesk Construction Cloud data, a Python backend, and the Gemini LLM via Streamlit.


Report Content

PROBLEM STATEMENT

OBJECTIVES, HYPOTHESIS & SCOPE

NEED OF STUDY

CAUSAL LOOP DIAGRAM

RII SURVEY ANALYSIS

STOCK & FLOW DIAGRAM

SCENARIOS

SCENARIOS- DEVIATION

PROTOTYPE PLATFORM

CONCLUSION

Project Video