This Directed Research Project investigates the usability gap in construction scheduling tools. Despite CPM's dominance, platforms like MSP and Primavera P6 function as compliance instruments rather than active planning tools. Using a Design Science Research approach, the study identified eight planning failure themes through field interviews, translated them into nine functional requirements, and developed a compound artefact of an eight-module prototype prioritizing planner-centric design, integrated production data, and intuitive dependency management. Beta evaluation against 19 practitioner-derived criteria validated the core thesis: CPM's logic is sound; its implementation environments need redesign.