This research develops a BIM-integrated workflow that automates construction progress monitoring using Artificial Intelligence. The study addresses a critical industry gap where BIM models, construction schedules, and site progress reports exist as disconnected systems, causing inefficiencies in 4D project control. A structured five-stage Large Language Model prompt chain was developed to generate BIM-aligned baseline schedules directly from element work packages, eliminating manual schedule re-breakdown. Weekly site photographs and 360-degree walkthroughs serve as evidence inputs, enabling automated planned versus actual comparisons with deviation detection. Validated on a live residential high-rise structural pilot, the framework achieved 79% effort reduction and 100% BIM-to-schedule linking accuracy.