This Directed Research Project explores how ambiguous and poorly structured contractual clauses lead to disputes, delays, and cost overruns in construction projects. Utilizing a mixed-method approach, the study identifies nine critical clauses—such as price adjustment, extension of time, and variation—through an extensive literature review. The research validates these findings through a Similarity and Variability (S&V) analysis of standard frameworks like FIDIC and CPWD, expert surveys from 65 professionals using Principal Component Analysis (PCA), and three real-world case studies. Ultimately, it recommends adopting balanced risk allocation and modernized practices to improve project outcomes.