This Directed Research Project (DRP) develops an early warning framework to identify potential delays, cost overruns, and claim risks in construction projects. The study applies Earned Value Management (EVM) indicators such as CPI and SPI along with defined threshold values to assess project performance. Monte Carlo Simulation is used to incorporate uncertainty and analyze risk probabilities. The framework is demonstrated using structured and simulated datasets to evaluate its effectiveness. Overall, the study presents a systematic and data-driven approach for improving project monitoring and supporting timely decision-making in construction projects.