UNDERGROUND METRO STATION PROJECT

The studio is regarding the study of Underground Metro station construction , execution monitoring and control. The study involves observations and analysis made from site activities and suggesting improvements wherever required. The topics covered are Project Site Layout and planning, Contractual conditions, Material management, Equipment management, Safety management, Lean construction tools like Value stream mapping and Foreman delay survey,Project risk management and Management Information system. 


Report Content

Project introduction & Site layout 3D Model

Construction sequence in Sketch up

Construction sequence in Sketch up

Safety management

Safety management & Job hazard analysis

Tools of Quality - Quality management

Lean Construction tools - Foreman Delay

Lean Construction tools - Foreman Delay

Lean Construction tools - Foreman Delay

Lean Construction tools - Foreman Delay