Kathiriya Jenish Ramesh

CT3013

JUNAGADH ZONE 3 WATER SUPPLY & SEWERAGE

In this studio we have learned how to efficiently design water supply and sewerage for the town or city. The design should be economical and best fit the given areas geological features. I have also learned that there are multiple ways to design a water supply and sewerage & client should be given all the possible iterations such that the client get to choose which is more important for a project economics or base constraints. Also while studying and referring CPHEEO I have noticed that there needs to be change in some factors of CPHEEO manual like revise constraints for hilly towns : minimum pipe diameter for hilly area, Minimum velocity for hilly areas etc.

View Additional Work

Report Content

INTRODUCTION & PROCESS

WATER DEMAND & TANK SIZING

WATER SUPPLY ITERTAIONS INITIAL

FINAL ITERATION & COST

SEWERAGE ITERATIONS

COSTING