For a richer surfing experience on our website, please update your browser. Update my browser now!
The project involves the analysis and design of an industrial production building. Key structural elements include lifting devices such as a Single EOT crane. The design adheres to IS 800 (Limit State Method) for structural steel, and wind load calculation as per IS 875 (part 3), seismic loads following IS 1893 Part 4. The scope includes designing the gantry girder, portal frame using plate section, and columns with brackets. Additionally project includes, comparative study of pin & fixed-supported portal frame. A significant challenge was that a column could not be placed at the Z2/9 grid, resulting in an increased gantry girder span and necessitating the provision of a jack beam to support the frame.