Malay Piyushkumar Gajera

CT2036

Green Valley Road

The Girmal–Shravaniya Link Road is an 11.82 km, two-lane Other District Road in Dang and Tapi, Gujarat, designed for 50 km/h. It replaces a 34.6 km, 52-minute trip and serves 20 villages, 14,844 people and waterfall tourism. Route 1 scored best of four options (4.84/5), and refining it cut the curves from 25 to 12. The design covers the alignments, retaining walls, 15 cross sections, lined drains with 12 hume pipe culverts, and a plastic–rubber pavement. Earthwork is about 30 lakh m³ of cut against 22.9 lakh m³ of fill. The estimated cost is 78.95 crore.

View Additional Work

Report Content

Study Area: Girmal to Shravaniya in Dang and Tapi, Gujarat, with 20 villages and 14,844 people. The 11.82 km new road replaces a 34.6 km, 52-minute route.

Terrain Study: Land use, contours, slope, aspect, roughness and streams of the 20,842 ha area. Forest covers 79.6%, so the road follows gentle slopes and avoids major stream paths.

Route Alternatives: Four routes compared on terrain, water crossings and land impact. Route 1 scored best (4.84/5) and was refined to the final 11.82 km alignment with 12 curves.

Horizontal Alignment: Plan of the 11.82 km alignment from Girmal to Shravaniya with all 12 curves and chainage details. Design criteria: ODR, 50 km/h ruling speed, 90 m ruling radius.

Vertical Alignment and Slope Protection: Vertical profile, design criteria and the slope assessment of the cut and fill stretches. Retaining walls protect the critical sections at CH 2+530 and 9+290.

Cross Sections and Earthwork: Fifteen cross sections from CH 0+000 to 11+820 and the mass haul diagram. Earthwork is about 30 lakh m³ of cut against 22.9 lakh m³ of fill, with a balance point near 7.9 km.

Drainage Design: Catchment areas, drain markings and 12 hume pipe culverts, with the side drain designed for 578 L/s. The lined 0.70 × 0.50 m drain has a bed slope of 1 in 130.

Soil, Material Testing and Pavement: Soil, aggregate and bitumen tests all pass, with a soaked CBR of 5.4%. The proposed pavement adds plastic–rubber bitumen and a C&D-waste subgrade, cutting total depth from 940 mm to 890 mm.

Road Safety, Intersections and Cost: Safety signage plan, junction layouts at both ends and the cost summary. Total estimated cost is ?78.95 crore (?6.68 crore/km), 80.9% of it cut and fill.

Optimizer Comparison and SWOT: The optimizer route (12.4 km, smoother profile) compared with the proposed path (11.9 km, serves more villages and tourist spots), followed by the SWOT analysis.