This project purpose is industrial set up for manufacturing herbicide product.so this report outcome of planning and controlling of an herbicide industrial project, so industry name is Fresh Field Agritech pvt. ltd. So in this project required per day manufacturing herbicide is 5 tonne.so that’s all the requirement project will planned, controlling and scheduling.

View Additional Work

Report Content

RISK ANALYSIS

WORK BRACK DOWN STRUCTURE

LEGAL FEASIBILITY

PROCURMENT APPROCH

milestone planning of project life cycle

Project Baseline Schedule with Tasks

Project Baseline Schedule with Tasks

Construction Plan: Resource Levelling, setting up Baseline

PROJECT PROGRESS AND MONITORING

Intermediate scheduling, completion forecast, project crashing